Grange Hall RD/CH4 over Piasa Creek
GoodJersey County, Illinois · 3.9MI S Ill 16 · Structure no. 042312500000000
- Built
- 1996
- 29 years old
- Condition
- Good
- inspected February 2023
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 109 ft
- 2 main spans
- Daily traffic
- 550
- 2022 count
- Owner
- County
- County Highway Agency
About this bridge
Grange Hall RD/CH4 over Piasa Creek is a prestressed concrete box beam or girders - multiple carrying Grange Hall RD/CH4 over Piasa Creek in Jersey County, Illinois. It was built in 1996, so it is 29 years old, younger than the Illinois average of 45.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 550 vehicles a day, roughly 7% of them trucks, projected to reach 581 by 2046. The structure is 109 ft (33.2 m) long and 24 ft wide. If it were closed, the detour would be 6.2 mi (10 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Grange Hall RD/CH4 over Piasa Creek built?
It was built in 1996, making it 29 years old in 2025.
What condition is Grange Hall RD/CH4 over Piasa Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2023.
How much traffic does Grange Hall RD/CH4 over Piasa Creek carry?
About 550 vehicles per day (2022 count), of which roughly 7% are trucks.
How long is Grange Hall RD/CH4 over Piasa Creek?
The structure is 109 ft (33.2 m) long with a longest span of 67 ft (20.4 m) and a deck 24 ft wide.
Who owns Grange Hall RD/CH4 over Piasa Creek?
It is owned by the County Highway Agency.