FAS 516 | Ch 12 over Salt Fork Vermilion Rive
GoodChampaign County, Illinois · 0.5 MI NE of Sidney · Structure no. 010029300000000
- Built
- 2021
- 4 years old
- Condition
- Good
- inspected August 2023
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 267 ft
- 2 main spans
- Daily traffic
- 800
- 2024 count
- Owner
- State
- State Highway Agency
About this bridge
FAS 516 | Ch 12 over Salt Fork Vermilion Rive is a steel continuous stringer/multi-beam or girder carrying FAS 516 | Ch 12 over Salt Fork Vermilion Rive in Champaign County, Illinois. It was built in 2021, so it is 4 years old, younger than the Illinois average of 45.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 800 vehicles a day, roughly 6% of them trucks, projected to reach 800 by 2046. The structure is 267 ft (81.4 m) long and 35 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 9 Excellent | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was FAS 516 | Ch 12 over Salt Fork Vermilion Rive built?
It was built in 2021, making it 4 years old in 2025.
What condition is FAS 516 | Ch 12 over Salt Fork Vermilion Rive in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2023.
How much traffic does FAS 516 | Ch 12 over Salt Fork Vermilion Rive carry?
About 800 vehicles per day (2024 count), of which roughly 6% are trucks.
How long is FAS 516 | Ch 12 over Salt Fork Vermilion Rive?
The structure is 267 ft (81.4 m) long with a longest span of 146 ft (44.6 m) and a deck 35 ft wide.
Who owns FAS 516 | Ch 12 over Salt Fork Vermilion Rive?
It is owned by the State Highway Agency.