TR 214 over Trib Plow Hollow Creek
GoodBureau County, Illinois · 2 MI SW Tiskilwa · Structure no. 006416000000000
- Built
- 2023
- 2 years old
- Condition
- Good
- inspected November 2023
- Type
- Culvert
- Concrete Continuous
- Length
- 22 ft
- 2 main spans
- Daily traffic
- 150
- 2020 count
- Owner
- Town / Township
- Town or Township Highway Agency
About this bridge
TR 214 over Trib Plow Hollow Creek is a concrete continuous culvert carrying TR 214 over Trib Plow Hollow Creek in Bureau County, Illinois. It was built in 2023, so it is 2 years old, younger than the Illinois average of 45.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 9 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 150 vehicles a day, roughly 5% of them trucks, projected to reach 152 by 2046. The structure is 22 ft (6.8 m) long and 20 ft wide. If it were closed, the detour would be 6.2 mi (10 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Channel and channel protection | 9 Excellent | No problems noted. |
| Culvert | 9 Excellent | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was TR 214 over Trib Plow Hollow Creek built?
It was built in 2023, making it 2 years old in 2025.
What condition is TR 214 over Trib Plow Hollow Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in November 2023.
How much traffic does TR 214 over Trib Plow Hollow Creek carry?
About 150 vehicles per day (2020 count), of which roughly 5% are trucks.
How long is TR 214 over Trib Plow Hollow Creek?
The structure is 22 ft (6.8 m) long with a longest span of 11 ft (3.3 m) and a deck 20 ft wide.
Who owns TR 214 over Trib Plow Hollow Creek?
It is owned by the Town or Township Highway Agency.