US Bridges

TR 255 over Drainage Canal

Fair

Adams County, Illinois · 3.1 MI Nnw Quincy · Structure no. 001327400000000

Built
1980
45 years old
Condition
Fair
inspected February 2024
Type
Box Beam or Girders - Multiple
Prestressed Concrete
Length
82 ft
1 main span
Daily traffic
125
2024 count
Owner
Town / Township
Town or Township Highway Agency

About this bridge

TR 255 over Drainage Canal is a prestressed concrete box beam or girders - multiple carrying TR 255 over Drainage Canal in Adams County, Illinois. It was built in 1980, so it is 45 years old, younger than the Illinois average of 45.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

It carries about 125 vehicles a day, roughly 10% of them trucks, projected to reach 101 by 2046. The structure is 82 ft (25 m) long and 27 ft wide. If it were closed, the detour would be 3.7 mi (6 km).

CarriesTR 255
CrossesDrainage Canal
Location3.1 MI Nnw Quincy
RouteCounty Highway 0
Coordinates40.00939, -91.43337
Functional classRural Local

Condition and inspection

Fair

The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

ComponentRatingMeaning
Deck5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Superstructure5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Substructure7 GoodSome minor problems.
Channel and channel protection6 SatisfactoryStructural elements show some minor deterioration.
Last inspectionFebruary 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation5: Somewhat better than minimum adequacy to tolerate being left in place as is
Deck geometry5: Somewhat better than minimum adequacy to tolerate being left in place as is
Waterway adequacy7: Better than present minimum criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating48.9 US tons
Inventory rating35.7 US tons

Structure

MaterialPrestressed Concrete
DeckConcrete, precast panels
Main spans1
Design loadHS 20
Structure length82 ft (25 m)
Longest span79 ft (24.1 m)
Deck width27 ft (8.1 m)
Roadway width27 ft (8.1 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic125 (2024)
Projected traffic101 by 2046
Trucks10%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed3.7 mi (6 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerTown or Township Highway Agency
Maintained byTown or Township Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was TR 255 over Drainage Canal built?

It was built in 1980, making it 45 years old in 2025.

What condition is TR 255 over Drainage Canal in?

The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in February 2024.

How much traffic does TR 255 over Drainage Canal carry?

About 125 vehicles per day (2024 count), of which roughly 10% are trucks.

How long is TR 255 over Drainage Canal?

The structure is 82 ft (25 m) long with a longest span of 79 ft (24.1 m) and a deck 27 ft wide.

Who owns TR 255 over Drainage Canal?

It is owned by the Town or Township Highway Agency.