S 1000 W over Trail Creek
PoorPosted for loadTeton County, Idaho · 0.1 N. 0.5 W. Victor · Structure no. 000000000033037
- Built
- 1995
- 30 years old
- Condition
- Poor
- inspected April 2024
- Type
- Tee Beam
- Concrete
- Length
- 25 ft
- 1 main span
- Daily traffic
- 60
- 2023 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
S 1000 W over Trail Creek is a concrete tee beam carrying S 1000 W over Trail Creek in Teton County, Idaho. It was built in 1995, so it is 30 years old, younger than the Idaho average of 45.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 4 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. Its operating status is: posted for load restriction.
It carries about 60 vehicles a day, roughly 5% of them trucks, projected to reach 90 by 2039. The structure is 25 ft (7.6 m) long and 24 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Superstructure | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Substructure | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was S 1000 W over Trail Creek built?
It was built in 1995, making it 30 years old in 2025.
What condition is S 1000 W over Trail Creek in?
The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in April 2024.
How much traffic does S 1000 W over Trail Creek carry?
About 60 vehicles per day (2023 count), of which roughly 5% are trucks.
How long is S 1000 W over Trail Creek?
The structure is 25 ft (7.6 m) long with a longest span of 24 ft (7.3 m) and a deck 24 ft wide.
Who owns S 1000 W over Trail Creek?
It is owned by the City or Municipal Highway Agency.