US Bridges

I 84 Ebl over Crestview Rd.Gs

Fair

Jerome County, Idaho · 10.4 W. Burley · Structure no. 000000000016300

Built
1966
59 years old
Condition
Fair
inspected March 2024
Type
Stringer/Multi-beam or Girder
Concrete
Length
114 ft
3 main spans
Daily traffic
11,500
2023 count
Owner
State
State Highway Agency

About this bridge

I 84 Ebl over Crestview Rd.Gs is a concrete stringer/multi-beam or girder carrying I 84 Ebl over Crestview Rd.Gs in Jerome County, Idaho. It was built in 1966, so it is 59 years old, older than the Idaho average of 45.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 6 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

It carries about 11,500 vehicles a day, roughly 30% of them trucks, projected to reach 17,250 by 2042. The structure is 114 ft (34.7 m) long and 41 ft wide. If it were closed, the detour would be 1.2 mi (2 km).

CarriesI 84 Ebl
CrossesCrestview Rd.Gs
Location10.4 W. Burley
RouteInterstate 84
StateIdaho
Coordinates42.57611, -113.98956
Functional classRural Principal Arterial - Interstate

Condition and inspection

Fair

The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

ComponentRatingMeaning
Deck6 SatisfactoryStructural elements show some minor deterioration.
Superstructure6 SatisfactoryStructural elements show some minor deterioration.
Substructure6 SatisfactoryStructural elements show some minor deterioration.
Last inspectionMarch 2024
Inspection intervalevery 48 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation6: Equal to present minimum criteria
Deck geometry6: Equal to present minimum criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating72 US tons
Inventory rating43 US tons

Structure

MaterialConcrete
DeckConcrete, cast-in-place
Main spans3
Design loadHS 20
Structure length114 ft (34.7 m)
Longest span37 ft (11.3 m)
Deck width41 ft (12.4 m)
Roadway width38 ft (11.6 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic11,500 (2023)
Projected traffic17,250 by 2042
Trucks30%
Lanes on structure2
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed1.2 mi (2 km)
TollOn a free road
National Highway SystemYes
Strategic Highway NetworkInterstate STRAHNET route

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusHistorical significance not determinable at this time
Work proposedReplacement because of substandard load-carrying capacity or roadway geometry
Estimated improvement cost$1.4 million (2020 estimate)
NavigationNot applicable (no waterway)

Frequently asked questions

When was I 84 Ebl over Crestview Rd.Gs built?

It was built in 1966, making it 59 years old in 2025.

What condition is I 84 Ebl over Crestview Rd.Gs in?

The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in March 2024.

How much traffic does I 84 Ebl over Crestview Rd.Gs carry?

About 11,500 vehicles per day (2023 count), of which roughly 30% are trucks.

How long is I 84 Ebl over Crestview Rd.Gs?

The structure is 114 ft (34.7 m) long with a longest span of 37 ft (11.3 m) and a deck 41 ft wide.

Who owns I 84 Ebl over Crestview Rd.Gs?

It is owned by the State Highway Agency.