US Bridges

US 20 over Garfield Ucon Canal

Fair

Jefferson County, Idaho · 1.4 S. Rigby · Structure no. 000000000012420

Built
1972
53 years old
Condition
Fair
inspected April 2022
Type
Frame
Concrete
Length
21 ft
1 main span
Daily traffic
34,500
2023 count
Owner
State
State Highway Agency

About this bridge

US 20 over Garfield Ucon Canal is a concrete frame carrying US 20 over Garfield Ucon Canal in Jefferson County, Idaho. It was built in 1972, so it is 53 years old, older than the Idaho average of 45.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 6 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

It carries about 34,500 vehicles a day, roughly 6% of them trucks, projected to reach 51,750 by 2042. The structure is 21 ft (6.4 m) long and 150 ft wide. If it were closed, the detour would be 1.2 mi (2 km).

CarriesUS 20
CrossesGarfield Ucon Canal
Location1.4 S. Rigby
RouteU.S. Route 20
StateIdaho
Coordinates43.65425, -111.92411
Functional classRural Principal Arterial - Other

Condition and inspection

Fair

The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

ComponentRatingMeaning
Deck6 SatisfactoryStructural elements show some minor deterioration.
Superstructure6 SatisfactoryStructural elements show some minor deterioration.
Substructure7 GoodSome minor problems.
Channel and channel protection8 Very GoodNo problems noted.
Last inspectionApril 2022
Inspection intervalevery 48 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation6: Equal to present minimum criteria
Deck geometry9: Superior to present desirable criteria
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating91.1 US tons
Inventory rating54 US tons

Structure

Structure typeFrame
MaterialConcrete
DeckConcrete, cast-in-place
Main spans1
Design loadHS 20
Structure length21 ft (6.4 m)
Longest span21 ft (6.4 m)
Deck width150 ft (45.7 m)
Roadway width148 ft (45.1 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic34,500 (2023)
Projected traffic51,750 by 2042
Trucks6%
Lanes on structure4
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed1.2 mi (2 km)
TollOn a free road
National Highway SystemYes

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusHistorical significance not determinable at this time
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was US 20 over Garfield Ucon Canal built?

It was built in 1972, making it 53 years old in 2025.

What condition is US 20 over Garfield Ucon Canal in?

The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in April 2022.

How much traffic does US 20 over Garfield Ucon Canal carry?

About 34,500 vehicles per day (2023 count), of which roughly 6% are trucks.

How long is US 20 over Garfield Ucon Canal?

The structure is 21 ft (6.4 m) long with a longest span of 21 ft (6.4 m) and a deck 150 ft wide.

Who owns US 20 over Garfield Ucon Canal?

It is owned by the State Highway Agency.