SH 200B over Strong Creek; E.Hope Br.
GoodBonner County, Idaho · In East Hope · Structure no. 000000000019081
- Built
- 2019
- 6 years old
- Condition
- Good
- inspected August 2022
- Type
- Box Beam or Girders - Single or Spread
- Prestressed Concrete
- Length
- 59 ft
- 1 main span
- Daily traffic
- 480
- 2023 count
- Owner
- State
- State Highway Agency
About this bridge
SH 200B over Strong Creek; E.Hope Br. is a prestressed concrete box beam or girders - single or spread carrying SH 200B over Strong Creek; E.Hope Br. in Bonner County, Idaho. It was built in 2019, so it is 6 years old, younger than the Idaho average of 45.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 480 vehicles a day, roughly 4% of them trucks, projected to reach 720 by 2042. The structure is 59 ft (18 m) long and 40 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 9 Excellent | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was SH 200B over Strong Creek; E.Hope Br. built?
It was built in 2019, making it 6 years old in 2025.
What condition is SH 200B over Strong Creek; E.Hope Br. in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2022.
How much traffic does SH 200B over Strong Creek; E.Hope Br. carry?
About 480 vehicles per day (2023 count), of which roughly 4% are trucks.
How long is SH 200B over Strong Creek; E.Hope Br.?
The structure is 59 ft (18 m) long with a longest span of 57 ft (17.3 m) and a deck 40 ft wide.
Who owns SH 200B over Strong Creek; E.Hope Br.?
It is owned by the State Highway Agency.