Finney Road over Polecat Creek
GoodPosted for loadTroup County, Georgia · 12 MI SE of Lagrange · Structure no. 000000028550150
- Built
- 1965
- 60 years old, rebuilt 2005
- Condition
- Good
- inspected September 2023
- Type
- Channel Beam
- Prestressed Concrete
- Length
- 75 ft
- 3 main spans
- Daily traffic
- 120
- 2024 count
- Owner
- County
- County Highway Agency
About this bridge
Finney Road over Polecat Creek is a prestressed concrete channel beam carrying Finney Road over Polecat Creek in Troup County, Georgia. It was built in 1965 and reconstructed in 2005, so it is 60 years old, older than the Georgia average of 47.5 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. Its operating status is: posted for load restriction.
It carries about 120 vehicles a day, roughly 1% of them trucks, projected to reach 735 by 2032. The structure is 75 ft (22.9 m) long and 26 ft wide. If it were closed, the detour would be 3.7 mi (6 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Finney Road over Polecat Creek built?
It was built in 1965, making it 60 years old in 2025. It was reconstructed in 2005.
What condition is Finney Road over Polecat Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in September 2023.
How much traffic does Finney Road over Polecat Creek carry?
About 120 vehicles per day (2024 count), of which roughly 1% are trucks.
How long is Finney Road over Polecat Creek?
The structure is 75 ft (22.9 m) long with a longest span of 25 ft (7.6 m) and a deck 26 ft wide.
Who owns Finney Road over Polecat Creek?
It is owned by the County Highway Agency.