US Bridges

US 82 / SR 520 EB over New River

GoodPosted for load

Tift County, Georgia · App 4 MI E of Tifton · Structure no. 000000027700180

Built
1971
54 years old
Condition
Good
inspected March 2024
Type
Tee Beam
Concrete
Length
120 ft
3 main spans
Daily traffic
15,100
2024 count
Owner
State
State Highway Agency

About this bridge

US 82 / SR 520 EB over New River is a concrete tee beam carrying US 82 / SR 520 EB over New River in Tift County, Georgia. It was built in 1971, so it is 54 years old, older than the Georgia average of 47.5 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. Its operating status is: posted for load restriction.

It carries about 15,100 vehicles a day, roughly 1% of them trucks, projected to reach 18,090 by 2031. The structure is 120 ft (36.6 m) long and 42 ft wide. If it were closed, the detour would be 1.2 mi (2 km).

CarriesUS 82 / SR 520 EB
CrossesNew River
LocationApp 4 MI E of Tifton
RouteU.S. Route 82
StateGeorgia
Coordinates31.44272, -83.47588
Functional classRural Principal Arterial - Other

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Channel and channel protection5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Last inspectionMarch 2024
Inspection intervalevery 24 months
Operating statusPosted for load restriction
ScourFoundations stable; scour within limits of footing or piles
Structural evaluation4: Meets minimum tolerable limits to be left in place as is
Deck geometry7: Better than present minimum criteria
Waterway adequacy6: Equal to present minimum criteria
Approach roadway alignment7: Better than present minimum criteria
Operating rating30 US tons
Inventory rating18 US tons

Structure

Structure typeTee Beam
MaterialConcrete
DeckConcrete, cast-in-place
Main spans3
Design loadHS 20 + Mod
Structure length120 ft (36.6 m)
Longest span40 ft (12.2 m)
Deck width42 ft (12.8 m)
Roadway width39 ft (11.8 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic15,100 (2024)
Projected traffic18,090 by 2031
Trucks1%
Lanes on structure2
Traffic directionOne-way traffic
CarriesHighway
CrossesWaterway
Detour if closed1.2 mi (2 km)
TollOn a free road
National Highway SystemYes
Strategic Highway NetworkNon-Interstate STRAHNET route

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost$703,000
NavigationNo navigation control on waterway

Frequently asked questions

When was US 82 / SR 520 EB over New River built?

It was built in 1971, making it 54 years old in 2025.

What condition is US 82 / SR 520 EB over New River in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in March 2024.

How much traffic does US 82 / SR 520 EB over New River carry?

About 15,100 vehicles per day (2024 count), of which roughly 1% are trucks.

How long is US 82 / SR 520 EB over New River?

The structure is 120 ft (36.6 m) long with a longest span of 40 ft (12.2 m) and a deck 42 ft wide.

Who owns US 82 / SR 520 EB over New River?

It is owned by the State Highway Agency.