Cs 913 - Wayside S over NS Railroad
GoodHabersham County, Georgia · In South Cornelia · Structure no. 000000013700390
- Built
- 1992
- 33 years old
- Condition
- Good
- inspected April 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 153 ft
- 3 main spans
- Daily traffic
- 1,290
- 2024 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
Cs 913 - Wayside S over NS Railroad is a steel continuous stringer/multi-beam or girder carrying Cs 913 - Wayside S over NS Railroad in Habersham County, Georgia. It was built in 1992, so it is 33 years old, younger than the Georgia average of 47.5 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 1,290 vehicles a day, roughly 1% of them trucks, projected to reach 2,580 by 2031. The structure is 153 ft (46.6 m) long and 37 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Cs 913 - Wayside S over NS Railroad built?
It was built in 1992, making it 33 years old in 2025.
What condition is Cs 913 - Wayside S over NS Railroad in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in April 2024.
How much traffic does Cs 913 - Wayside S over NS Railroad carry?
About 1,290 vehicles per day (2024 count), of which roughly 1% are trucks.
How long is Cs 913 - Wayside S over NS Railroad?
The structure is 153 ft (46.6 m) long with a longest span of 67 ft (20.4 m) and a deck 37 ft wide.
Who owns Cs 913 - Wayside S over NS Railroad?
It is owned by the City or Municipal Highway Agency.