US Bridges

I-285 Ccb to SR 40 over SR 400 Nbl (US19)

Good

Fulton County, Georgia · In N Fulton · Structure no. 000000012154120

Built
2022
3 years old
Condition
Good
inspected June 2023
Type
Stringer/Multi-beam or Girder
Concrete
Length
736 ft
7 main spans
Daily traffic
9,940
2024 count
Owner
State
State Highway Agency

About this bridge

I-285 Ccb to SR 40 over SR 400 Nbl (US19) is a concrete stringer/multi-beam or girder carrying I-285 Ccb to SR 40 over SR 400 Nbl (US19) in Fulton County, Georgia. It was built in 2022, so it is 3 years old, younger than the Georgia average of 47.5 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. Its operating status is: new structure not yet open to traffic.

It carries about 9,940 vehicles a day, roughly 6% of them trucks, projected to reach 16,750 by 2039. The structure is 736 ft (224.3 m) long and 39 ft wide. If it were closed, the detour would be 1.2 mi (2 km).

CarriesI-285 Ccb to SR 40
CrossesSR 400 Nbl (US19)
LocationIn N Fulton
RouteInterstate 285
StateGeorgia
Coordinates33.91367, -84.35658
Functional classUrban Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure8 Very GoodNo problems noted.
Substructure8 Very GoodNo problems noted.
Last inspectionJune 2023
Inspection intervalevery 24 months
Operating statusNew structure not yet open to traffic
ScourBridge not over waterway
Structural evaluation8: Equal to present desirable criteria
Deck geometry9: Superior to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating87 US tons
Inventory rating48.9 US tons

Structure

MaterialConcrete
DeckConcrete, cast-in-place
Main spans7
Design loadHL 93
Structure length736 ft (224.3 m)
Longest span108 ft (32.9 m)
Deck width39 ft (11.9 m)
Roadway width35 ft (10.7 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic9,940 (2024)
Projected traffic16,750 by 2039
Trucks6%
Lanes on structure1
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed1.2 mi (2 km)
TollOn a free road
National Highway SystemYes
Strategic Highway NetworkInterstate STRAHNET route

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNot applicable (no waterway)

Frequently asked questions

When was I-285 Ccb to SR 40 over SR 400 Nbl (US19) built?

It was built in 2022, making it 3 years old in 2025.

What condition is I-285 Ccb to SR 40 over SR 400 Nbl (US19) in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in June 2023.

How much traffic does I-285 Ccb to SR 40 over SR 400 Nbl (US19) carry?

About 9,940 vehicles per day (2024 count), of which roughly 6% are trucks.

How long is I-285 Ccb to SR 40 over SR 400 Nbl (US19)?

The structure is 736 ft (224.3 m) long with a longest span of 108 ft (32.9 m) and a deck 39 ft wide.

Who owns I-285 Ccb to SR 40 over SR 400 Nbl (US19)?

It is owned by the State Highway Agency.