Fulton County, Georgia · I-75 & I-20 Interchange · Structure no. 000000012107060

Built
1989
36 years old
Condition
Good
inspected July 2023
Type
Box Beam or Girders - Single or Spread
Prestressed Concrete Continuous
Length
520 ft
3 main spans
Daily traffic
6,805
2024 count
Owner
State
State Highway Agency

About this bridge

I-75 Rmp to I-20WB over M9164 & Rmp- M9166 & Rmp is a prestressed concrete continuous box beam or girders - single or spread carrying I-75 Rmp to I-20WB over M9164 & Rmp- M9166 & Rmp in Fulton County, Georgia. It was built in 1989, so it is 36 years old, younger than the Georgia average of 47.5 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 6,805 vehicles a day, roughly 1% of them trucks, projected to reach 46,425 by 2032. The structure is 520 ft (158.5 m) long and 46 ft wide. If it were closed, the detour would be 1.9 mi (3 km).

CarriesI-75 Rmp to I-20WB
CrossesM9164 & Rmp- M9166 & Rmp
LocationI-75 & I-20 Interchange
RouteInterstate 75
StateGeorgia
Coordinates33.7458, -84.39387
Functional classUrban Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Last inspectionJuly 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation7: Better than present minimum criteria
Deck geometry9: Superior to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating61 US tons
Inventory rating35.9 US tons

Structure

MaterialPrestressed Concrete Continuous
DeckConcrete, cast-in-place
Main spans3
Design loadHS 20 + Mod
Structure length520 ft (158.5 m)
Longest span190 ft (57.9 m)
Deck width46 ft (14.1 m)
Roadway width43 ft (13.1 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic6,805 (2024)
Projected traffic46,425 by 2032
Trucks1%
Lanes on structure1
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed1.9 mi (3 km)
TollOn a free road
National Highway SystemYes

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost$2.2 million
NavigationNot applicable (no waterway)

Frequently asked questions

When was I-75 Rmp to I-20WB over M9164 & Rmp- M9166 & Rmp built?

It was built in 1989, making it 36 years old in 2025.

What condition is I-75 Rmp to I-20WB over M9164 & Rmp- M9166 & Rmp in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in July 2023.

How much traffic does I-75 Rmp to I-20WB over M9164 & Rmp- M9166 & Rmp carry?

About 6,805 vehicles per day (2024 count), of which roughly 1% are trucks.

How long is I-75 Rmp to I-20WB over M9164 & Rmp- M9166 & Rmp?

The structure is 520 ft (158.5 m) long with a longest span of 190 ft (57.9 m) and a deck 46 ft wide.

Who owns I-75 Rmp to I-20WB over M9164 & Rmp- M9166 & Rmp?

It is owned by the State Highway Agency.