DeKalb County, Georgia · 2.4 MI E of Chamblee · Structure no. 000000008902760

Built
1987
38 years old
Condition
Good
inspected August 2024
Type
Box Beam or Girders - Single or Spread
Prestressed Concrete Continuous
Length
2,373 ft
14 main spans
Daily traffic
6,805
2024 count
Owner
State
State Highway Agency

About this bridge

Rmp I-285 to I-85 over 2 I-85 RMPS-4 I-285 Rmps is a prestressed concrete continuous box beam or girders - single or spread carrying Rmp I-285 to I-85 over 2 I-85 RMPS-4 I-285 Rmps in DeKalb County, Georgia. It was built in 1987, so it is 38 years old, younger than the Georgia average of 47.5 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 6,805 vehicles a day, roughly 1% of them trucks, projected to reach 60,435 by 2031. The structure is 2,373 ft (723.3 m) long and 45 ft wide. If it were closed, the detour would be 1.2 mi (2 km).

CarriesRmp I-285 to I-85
Crosses2 I-85 RMPS-4 I-285 Rmps
Location2.4 MI E of Chamblee
RouteInterstate 285
StateGeorgia
Coordinates33.8923, -84.25924
Functional classUrban Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Last inspectionAugust 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation7: Better than present minimum criteria
Deck geometry9: Superior to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating61 US tons
Inventory rating35.9 US tons

Structure

MaterialPrestressed Concrete Continuous
DeckConcrete, cast-in-place
Main spans14
Design loadHS 20 + Mod
Structure length2,373 ft (723.3 m)
Longest span227 ft (69.2 m)
Deck width45 ft (13.8 m)
Roadway width42 ft (12.8 m)
Vertical clearance over deck19 ft (5.9 m)

Traffic and service

Average daily traffic6,805 (2024)
Projected traffic60,435 by 2031
Trucks1%
Lanes on structure2
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed1.2 mi (2 km)
TollOn a free road
National Highway SystemYes
Strategic Highway NetworkInterstate STRAHNET route

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost$13.9 million
NavigationNot applicable (no waterway)

Frequently asked questions

When was Rmp I-285 to I-85 over 2 I-85 RMPS-4 I-285 Rmps built?

It was built in 1987, making it 38 years old in 2025.

What condition is Rmp I-285 to I-85 over 2 I-85 RMPS-4 I-285 Rmps in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2024.

How much traffic does Rmp I-285 to I-85 over 2 I-85 RMPS-4 I-285 Rmps carry?

About 6,805 vehicles per day (2024 count), of which roughly 1% are trucks.

How long is Rmp I-285 to I-85 over 2 I-85 RMPS-4 I-285 Rmps?

The structure is 2,373 ft (723.3 m) long with a longest span of 227 ft (69.2 m) and a deck 45 ft wide.

Who owns Rmp I-285 to I-85 over 2 I-85 RMPS-4 I-285 Rmps?

It is owned by the State Highway Agency.