Chamblee-Tucker RD over I-285 (sr 407)
GoodDeKalb County, Georgia · 2 MI S of Doraville · Structure no. 000000008901990
- Built
- 1981
- 44 years old
- Condition
- Good
- inspected July 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 230 ft
- 2 main spans
- Daily traffic
- 25,200
- 2024 count
- Owner
- State
- State Highway Agency
About this bridge
Chamblee-Tucker RD over I-285 (sr 407) is a steel continuous stringer/multi-beam or girder carrying Chamblee-Tucker RD over I-285 (sr 407) in DeKalb County, Georgia. It was built in 1981, so it is 44 years old, younger than the Georgia average of 47.5 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 25,200 vehicles a day, roughly 1% of them trucks, projected to reach 19,605 by 2031. The structure is 230 ft (70.1 m) long and 94 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Chamblee-Tucker RD over I-285 (sr 407) built?
It was built in 1981, making it 44 years old in 2025.
What condition is Chamblee-Tucker RD over I-285 (sr 407) in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in July 2024.
How much traffic does Chamblee-Tucker RD over I-285 (sr 407) carry?
About 25,200 vehicles per day (2024 count), of which roughly 1% are trucks.
How long is Chamblee-Tucker RD over I-285 (sr 407)?
The structure is 230 ft (70.1 m) long with a longest span of 137 ft (41.8 m) and a deck 94 ft wide.
Who owns Chamblee-Tucker RD over I-285 (sr 407)?
It is owned by the State Highway Agency.