US Bridges

I-95 (sbl) over Pipe Makers Canal

Good

Chatham County, Georgia · 1 MI N of Pooler · Structure no. 000000005101160

Built
1976
49 years old, rebuilt 1996
Condition
Good
inspected June 2024
Type
Tee Beam
Concrete
Length
108 ft
3 main spans
Daily traffic
61,100
2024 count
Owner
State
State Highway Agency

About this bridge

I-95 (sbl) over Pipe Makers Canal is a concrete tee beam carrying I-95 (sbl) over Pipe Makers Canal in Chatham County, Georgia. It was built in 1976 and reconstructed in 1996, so it is 49 years old, older than the Georgia average of 47.5 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 61,100 vehicles a day, roughly 1% of them trucks, projected to reach 105,195 by 2032. The structure is 108 ft (32.9 m) long and 79 ft wide. If it were closed, the detour would be 1.2 mi (2 km).

CarriesI-95 (sbl)
CrossesPipe Makers Canal
Location1 MI N of Pooler
RouteInterstate 95
StateGeorgia
Coordinates32.13168, -81.23999
Functional classUrban Principal Arterial - Interstate

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck8 Very GoodNo problems noted.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Channel and channel protection8 Very GoodNo problems noted.
Last inspectionJune 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourScour critical; foundations unstable for calculated scour conditions
Structural evaluation6: Equal to present minimum criteria
Deck geometry9: Superior to present desirable criteria
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating46 US tons
Inventory rating26.9 US tons

Structure

Structure typeTee Beam
MaterialConcrete
DeckConcrete, cast-in-place
Main spans3
Design loadHS 20 + Mod
Structure length108 ft (32.9 m)
Longest span36 ft (11 m)
Deck width79 ft (24.2 m)
Roadway width76 ft (23.2 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic61,100 (2024)
Projected traffic105,195 by 2032
Trucks1%
Lanes on structure3
Traffic directionOne-way traffic
CarriesHighway
CrossesWaterway
Detour if closed1.2 mi (2 km)
TollOn a free road
National Highway SystemYes
Strategic Highway NetworkInterstate STRAHNET route

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost$806,000
NavigationNo navigation control on waterway

Frequently asked questions

When was I-95 (sbl) over Pipe Makers Canal built?

It was built in 1976, making it 49 years old in 2025. It was reconstructed in 1996.

What condition is I-95 (sbl) over Pipe Makers Canal in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in June 2024.

How much traffic does I-95 (sbl) over Pipe Makers Canal carry?

About 61,100 vehicles per day (2024 count), of which roughly 1% are trucks.

How long is I-95 (sbl) over Pipe Makers Canal?

The structure is 108 ft (32.9 m) long with a longest span of 36 ft (11 m) and a deck 79 ft wide.

Who owns I-95 (sbl) over Pipe Makers Canal?

It is owned by the State Highway Agency.