Village Blvd (nb) over Liptog Canal
GoodPalm Beach County, Florida · 2MI S of 45th ST CR-702 · Structure no. 937711
- Built
- 1983
- 42 years old
- Condition
- Good
- inspected January 2024
- Type
- Slab
- Prestressed Concrete
- Length
- 92 ft
- 3 main spans
- Daily traffic
- 1,440
- 2024 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
Village Blvd (nb) over Liptog Canal is a prestressed concrete slab carrying Village Blvd (nb) over Liptog Canal in Palm Beach County, Florida. It was built in 1983, so it is 42 years old, older than the Florida average of 41.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 1,440 vehicles a day, roughly 2% of them trucks, projected to reach 1,665 by 2042. The structure is 92 ft (28 m) long and 39 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Village Blvd (nb) over Liptog Canal built?
It was built in 1983, making it 42 years old in 2025.
What condition is Village Blvd (nb) over Liptog Canal in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in January 2024.
How much traffic does Village Blvd (nb) over Liptog Canal carry?
About 1,440 vehicles per day (2024 count), of which roughly 2% are trucks.
How long is Village Blvd (nb) over Liptog Canal?
The structure is 92 ft (28 m) long with a longest span of 30 ft (9.2 m) and a deck 39 ft wide.
Who owns Village Blvd (nb) over Liptog Canal?
It is owned by the City or Municipal Highway Agency.