Project H over Canal L-402
GoodOrange County, Florida · 0.02MI S. of S Studio DR · Structure no. 756431
- Built
- 2019
- 6 years old
- Condition
- Good
- inspected December 2023
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete
- Length
- 90 ft
- 1 main span
- Daily traffic
- 1,001
- 2023 count
- Owner
- Private
- Private (other than railroad)
About this bridge
Project H over Canal L-402 is a prestressed concrete stringer/multi-beam or girder carrying Project H over Canal L-402 in Orange County, Florida. It was built in 2019, so it is 6 years old, younger than the Florida average of 41.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 1,001 vehicles a day, roughly 1% of them trucks, projected to reach 2,001 by 2042. The structure is 90 ft (27.4 m) long and 39 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Project H over Canal L-402 built?
It was built in 2019, making it 6 years old in 2025.
What condition is Project H over Canal L-402 in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in December 2023.
How much traffic does Project H over Canal L-402 carry?
About 1,001 vehicles per day (2023 count), of which roughly 1% are trucks.
How long is Project H over Canal L-402?
The structure is 90 ft (27.4 m) long with a longest span of 90 ft (27.4 m) and a deck 39 ft wide.
Who owns Project H over Canal L-402?
It is owned by the Private (other than railroad).