I-4 WB & El WB over Division Avenue
GoodOrange County, Florida · 0.2MI W/O SR-408 · Structure no. 750789
- Built
- 2020
- 5 years old
- Condition
- Good
- inspected April 2024
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete
- Length
- 231 ft
- 2 main spans
- Daily traffic
- 82,500
- 2022 count
- Owner
- State
- State Highway Agency
About this bridge
I-4 WB & El WB over Division Avenue is a prestressed concrete stringer/multi-beam or girder carrying I-4 WB & El WB over Division Avenue in Orange County, Florida. It was built in 2020, so it is 5 years old, younger than the Florida average of 41.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 82,500 vehicles a day, roughly 7% of them trucks, projected to reach 143,138 by 2042. The structure is 231 ft (70.5 m) long and 133 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was I-4 WB & El WB over Division Avenue built?
It was built in 2020, making it 5 years old in 2025.
What condition is I-4 WB & El WB over Division Avenue in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in April 2024.
How much traffic does I-4 WB & El WB over Division Avenue carry?
About 82,500 vehicles per day (2022 count), of which roughly 7% are trucks.
How long is I-4 WB & El WB over Division Avenue?
The structure is 231 ft (70.5 m) long with a longest span of 116 ft (35.3 m) and a deck 133 ft wide.
Who owns I-4 WB & El WB over Division Avenue?
It is owned by the State Highway Agency.