IRR BIA RTE 182 over West Feeder Canal
FairHendry County, Florida · 9KM W Int. BIA 182 & 1281 · Structure no. 00000000000S304
- Built
- 1965
- 60 years old
- Condition
- Fair
- inspected June 2024
- Type
- Slab
- Prestressed Concrete
- Length
- 90 ft
- 3 main spans
- Daily traffic
- 120
- 2021 count
- Owner
- Federal
- Bureau of Indian Affairs
About this bridge
IRR BIA RTE 182 over West Feeder Canal is a prestressed concrete slab carrying IRR BIA RTE 182 over West Feeder Canal in Hendry County, Florida. It was built in 1965, so it is 60 years old, older than the Florida average of 41.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 120 vehicles a day, roughly 3% of them trucks, projected to reach 125 by 2039. The structure is 90 ft (27.4 m) long and 25 ft wide. If it were closed, the detour would be 16.2 mi (26 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Channel and channel protection | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was IRR BIA RTE 182 over West Feeder Canal built?
It was built in 1965, making it 60 years old in 2025.
What condition is IRR BIA RTE 182 over West Feeder Canal in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in June 2024.
How much traffic does IRR BIA RTE 182 over West Feeder Canal carry?
About 120 vehicles per day (2021 count), of which roughly 3% are trucks.
How long is IRR BIA RTE 182 over West Feeder Canal?
The structure is 90 ft (27.4 m) long with a longest span of 30 ft (9.1 m) and a deck 25 ft wide.
Who owns IRR BIA RTE 182 over West Feeder Canal?
It is owned by the Bureau of Indian Affairs.