CR 25 (95th Ave.) over Loveland Greeley Canal

Good

Weld County, Colorado · 0.1 MI N of CO RD 52 · Structure no. WEL025.0-052.0A

Built
1962
63 years old, rebuilt 2007
Condition
Good
inspected April 2024
Type
Stringer/Multi-beam or Girder
Steel
Length
30 ft
1 main span
Daily traffic
198
2023 count
Owner
County
County Highway Agency

About this bridge

CR 25 (95th Ave.) over Loveland Greeley Canal is a steel stringer/multi-beam or girder carrying CR 25 (95th Ave.) over Loveland Greeley Canal in Weld County, Colorado. It was built in 1962 and reconstructed in 2007, so it is 63 years old, older than the Colorado average of 42.2 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 198 vehicles a day, roughly 58% of them trucks, projected to reach 281 by 2042. The structure is 30 ft (9.2 m) long and 24 ft wide. If it were closed, the detour would be 3.1 mi (5 km).

CarriesCR 25 (95th Ave.)
CrossesLoveland Greeley Canal
Location0.1 MI N of CO RD 52
RouteCounty Highway 0
Coordinates40.365, -104.83202
Functional classRural Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Channel and channel protection8 Very GoodNo problems noted.
Last inspectionApril 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation7: Better than present minimum criteria
Deck geometry5: Somewhat better than minimum adequacy to tolerate being left in place as is
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating52.6 US tons
Inventory rating31.5 US tons

Structure

MaterialSteel
DeckCorrugated steel
Main spans1
Design loadHS 20
Structure length30 ft (9.2 m)
Longest span28 ft (8.4 m)
Deck width24 ft (7.4 m)
Roadway width24 ft (7.3 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic198 (2023)
Projected traffic281 by 2042
Trucks58%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed3.1 mi (5 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCounty Highway Agency
Maintained byCounty Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was CR 25 (95th Ave.) over Loveland Greeley Canal built?

It was built in 1962, making it 63 years old in 2025. It was reconstructed in 2007.

What condition is CR 25 (95th Ave.) over Loveland Greeley Canal in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in April 2024.

How much traffic does CR 25 (95th Ave.) over Loveland Greeley Canal carry?

About 198 vehicles per day (2023 count), of which roughly 58% are trucks.

How long is CR 25 (95th Ave.) over Loveland Greeley Canal?

The structure is 30 ft (9.2 m) long with a longest span of 28 ft (8.4 m) and a deck 24 ft wide.

Who owns CR 25 (95th Ave.) over Loveland Greeley Canal?

It is owned by the County Highway Agency.