County Road 3 over Larimer and Weld Canal
FairLarimer County, Colorado · 0.5 MI N of CO RD 44 · Structure no. LR3-0.5-44-A
- Built
- 1960
- 65 years old, rebuilt 2005
- Condition
- Fair
- inspected March 2025
- Type
- Slab
- Prestressed Concrete
- Length
- 46 ft
- 1 main span
- Daily traffic
- 412
- 2023 count
- Owner
- County
- County Highway Agency
About this bridge
County Road 3 over Larimer and Weld Canal is a prestressed concrete slab carrying County Road 3 over Larimer and Weld Canal in Larimer County, Colorado. It was built in 1960 and reconstructed in 2005, so it is 65 years old, older than the Colorado average of 42.2 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 6 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 412 vehicles a day, roughly 33% of them trucks, projected to reach 515 by 2043. The structure is 46 ft (14 m) long and 28 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was County Road 3 over Larimer and Weld Canal built?
It was built in 1960, making it 65 years old in 2025. It was reconstructed in 2005.
What condition is County Road 3 over Larimer and Weld Canal in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in March 2025.
How much traffic does County Road 3 over Larimer and Weld Canal carry?
About 412 vehicles per day (2023 count), of which roughly 33% are trucks.
How long is County Road 3 over Larimer and Weld Canal?
The structure is 46 ft (14 m) long with a longest span of 42 ft (12.8 m) and a deck 28 ft wide.
Who owns County Road 3 over Larimer and Weld Canal?
It is owned by the County Highway Agency.