Ramp to US 285 Nbd over Parmalee Gulch R
GoodJefferson County, Colorado · Indian Hills RD Intsctn · Structure no. F-16-SO
- Built
- 1993
- 32 years old
- Condition
- Good
- inspected August 2023
- Type
- Culvert
- Concrete
- Length
- 42 ft
- 3 main spans
- Daily traffic
- 13,500
- 2020 count
- Owner
- State
- State Highway Agency
About this bridge
Ramp to US 285 Nbd over Parmalee Gulch R is a concrete culvert carrying Ramp to US 285 Nbd over Parmalee Gulch R in Jefferson County, Colorado. It was built in 1993, so it is 32 years old, younger than the Colorado average of 42.2 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 13,500 vehicles a day, roughly 3% of them trucks, projected to reach 17,010 by 2040. The structure is 42 ft (12.9 m) long and 57 ft wide. If it were closed, the detour would be 0.6 mi (1 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Channel and channel protection | 7 Good | Some minor problems. |
| Culvert | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Ramp to US 285 Nbd over Parmalee Gulch R built?
It was built in 1993, making it 32 years old in 2025.
What condition is Ramp to US 285 Nbd over Parmalee Gulch R in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2023.
How much traffic does Ramp to US 285 Nbd over Parmalee Gulch R carry?
About 13,500 vehicles per day (2020 count), of which roughly 3% are trucks.
How long is Ramp to US 285 Nbd over Parmalee Gulch R?
The structure is 42 ft (12.9 m) long with a longest span of 16 ft (4.8 m) and a deck 57 ft wide.
Who owns Ramp to US 285 Nbd over Parmalee Gulch R?
It is owned by the State Highway Agency.