FairDenver County, Colorado · .2 Miles West of Tower RD · Structure no. D-25-FC-020A
- Built
- 2000
- 25 years old
- Condition
- Fair
- inspected November 2024
- Type
- Box Beam or Girders - Single or Spread
- Prestressed Concrete
- Length
- 80 ft
- 1 main span
- Daily traffic
- 14,732
- 2021 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
EB E 56th Avenue over Bike Path and Flow First is a prestressed concrete box beam or girders - single or spread carrying EB E 56th Avenue over Bike Path and Flow First in Denver County, Colorado. It was built in 2000, so it is 25 years old, younger than the Colorado average of 42.2 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 14,732 vehicles a day, roughly 2% of them trucks, projected to reach 16,353 by 2041. The structure is 80 ft (24.4 m) long and 41 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was EB E 56th Avenue over Bike Path and Flow First built?
It was built in 2000, making it 25 years old in 2025.
What condition is EB E 56th Avenue over Bike Path and Flow First in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in November 2024.
How much traffic does EB E 56th Avenue over Bike Path and Flow First carry?
About 14,732 vehicles per day (2021 count), of which roughly 2% are trucks.
How long is EB E 56th Avenue over Bike Path and Flow First?
The structure is 80 ft (24.4 m) long with a longest span of 75 ft (22.8 m) and a deck 41 ft wide.
Who owns EB E 56th Avenue over Bike Path and Flow First?
It is owned by the City or Municipal Highway Agency.