County Road #105 over Willow Slough Bypass
FairYolo County, California · Just North of C.R. # 29 · Structure no. 22C0146
- Built
- 1976
- 49 years old
- Condition
- Fair
- inspected January 2024
- Type
- Slab
- Concrete Continuous
- Length
- 330 ft
- 11 main spans
- Daily traffic
- 700
- 2014 count
- Owner
- County
- County Highway Agency
About this bridge
County Road #105 over Willow Slough Bypass is a concrete continuous slab carrying County Road #105 over Willow Slough Bypass in Yolo County, California. It was built in 1976, so it is 49 years old, younger than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 700 vehicles a day, roughly 25% of them trucks, projected to reach 1,345 by 2042. The structure is 330 ft (100.5 m) long and 29 ft wide. If it were closed, the detour would be 5 mi (8 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was County Road #105 over Willow Slough Bypass built?
It was built in 1976, making it 49 years old in 2025.
What condition is County Road #105 over Willow Slough Bypass in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in January 2024.
How much traffic does County Road #105 over Willow Slough Bypass carry?
About 700 vehicles per day (2014 count), of which roughly 25% are trucks.
How long is County Road #105 over Willow Slough Bypass?
The structure is 330 ft (100.5 m) long with a longest span of 32 ft (9.7 m) and a deck 29 ft wide.
Who owns County Road #105 over Willow Slough Bypass?
It is owned by the County Highway Agency.