Islay ST over Mission Creek
PoorSanta Barbara County, California · At Castillo ST · Structure no. 51C0289
- Built
- 1982
- 43 years old
- Condition
- Poor
- inspected March 2023
- Type
- Slab
- Concrete Continuous
- Length
- 53 ft
- 2 main spans
- Daily traffic
- 700
- 2005 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
Islay ST over Mission Creek is a concrete continuous slab carrying Islay ST over Mission Creek in Santa Barbara County, California. It was built in 1982, so it is 43 years old, younger than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 4 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
It carries about 700 vehicles a day, roughly 1% of them trucks, projected to reach 657 by 2043. The structure is 53 ft (16.2 m) long and 27 ft wide. If it were closed, the detour would be 123.7 mi (199 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Channel and channel protection | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Islay ST over Mission Creek built?
It was built in 1982, making it 43 years old in 2025.
What condition is Islay ST over Mission Creek in?
The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in March 2023.
How much traffic does Islay ST over Mission Creek carry?
About 700 vehicles per day (2005 count), of which roughly 1% are trucks.
How long is Islay ST over Mission Creek?
The structure is 53 ft (16.2 m) long with a longest span of 31 ft (9.4 m) and a deck 27 ft wide.
Who owns Islay ST over Mission Creek?
It is owned by the City or Municipal Highway Agency.