US Bridges

Portola Road over Alembique Creek

Good

San Mateo County, California · 0.25 MI E of State RTE 84 · Structure no. 35C0214

Built
2021
4 years old
Condition
Good
inspected May 2024
Type
Slab
Prestressed Concrete Continuous
Length
87 ft
2 main spans
Daily traffic
2,969
2019 count
Owner
Town / Township
Town or Township Highway Agency

About this bridge

Portola Road over Alembique Creek is a prestressed concrete continuous slab carrying Portola Road over Alembique Creek in San Mateo County, California. It was built in 2021, so it is 4 years old, younger than the California average of 54.8 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 2,969 vehicles a day, roughly 1% of them trucks, projected to reach 6,307 by 2041. The structure is 87 ft (26.5 m) long and 30 ft wide. If it were closed, the detour would be 5 mi (8 km).

CarriesPortola Road
CrossesAlembique Creek
Location0.25 MI E of State RTE 84
RouteCity Street 0
Coordinates37.40433, -122.25448
Functional classUrban Minor Arterial

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Channel and channel protection6 SatisfactoryStructural elements show some minor deterioration.
Last inspectionMay 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour within limits of footing or piles
Structural evaluation7: Better than present minimum criteria
Deck geometry3: Basically intolerable, requiring high priority of corrective action
Waterway adequacy6: Equal to present minimum criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating59.6 US tons
Inventory rating35.7 US tons

Structure

Structure typeSlab
MaterialPrestressed Concrete Continuous
DeckConcrete, cast-in-place
Main spans2
Design loadHL 93
Structure length87 ft (26.5 m)
Longest span42 ft (12.8 m)
Deck width30 ft (9.1 m)
Roadway width27 ft (8.1 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic2,969 (2019)
Projected traffic6,307 by 2041
Trucks1%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway and pedestrian
CrossesWaterway
Detour if closed5 mi (8 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerTown or Township Highway Agency
Maintained byTown or Township Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNot applicable (no waterway)

Frequently asked questions

When was Portola Road over Alembique Creek built?

It was built in 2021, making it 4 years old in 2025.

What condition is Portola Road over Alembique Creek in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in May 2024.

How much traffic does Portola Road over Alembique Creek carry?

About 2,969 vehicles per day (2019 count), of which roughly 1% are trucks.

How long is Portola Road over Alembique Creek?

The structure is 87 ft (26.5 m) long with a longest span of 42 ft (12.8 m) and a deck 30 ft wide.

Who owns Portola Road over Alembique Creek?

It is owned by the Town or Township Highway Agency.