Airport Way over San Joaquin River 06
FairSan Joaquin County, California · 0.5 MI NE of Kasson RD · Structure no. 29C0187
- Built
- 1965
- 60 years old, rebuilt 2008
- Condition
- Fair
- inspected June 2024
- Type
- Box Beam or Girders - Multiple
- Concrete Continuous
- Length
- 546 ft
- 5 main spans
- Daily traffic
- 2,042
- 2015 count
- Owner
- County
- County Highway Agency
About this bridge
Airport Way over San Joaquin River 06 is a concrete continuous box beam or girders - multiple carrying Airport Way over San Joaquin River 06 in San Joaquin County, California. It was built in 1965 and reconstructed in 2008, so it is 60 years old, older than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 2,042 vehicles a day, roughly 5% of them trucks, projected to reach 2,999 by 2046. The structure is 546 ft (166.4 m) long and 32 ft wide. If it were closed, the detour would be 23 mi (37 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Airport Way over San Joaquin River 06 built?
It was built in 1965, making it 60 years old in 2025. It was reconstructed in 2008.
What condition is Airport Way over San Joaquin River 06 in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in June 2024.
How much traffic does Airport Way over San Joaquin River 06 carry?
About 2,042 vehicles per day (2015 count), of which roughly 5% are trucks.
How long is Airport Way over San Joaquin River 06?
The structure is 546 ft (166.4 m) long with a longest span of 120 ft (36.6 m) and a deck 32 ft wide.
Who owns Airport Way over San Joaquin River 06?
It is owned by the County Highway Agency.