Genesee Ave over San Clemente Canyon Crk
GoodSan Diego County, California · 0.2 MI S/O of SR 52 · Structure no. 57C0223
- Built
- 1966
- 59 years old, rebuilt 1970
- Condition
- Good
- inspected September 2023
- Type
- Slab
- Concrete Continuous
- Length
- 155 ft
- 5 main spans
- Daily traffic
- 29,800
- 2019 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
Genesee Ave over San Clemente Canyon Crk is a concrete continuous slab carrying Genesee Ave over San Clemente Canyon Crk in San Diego County, California. It was built in 1966 and reconstructed in 1970, so it is 59 years old, older than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 29,800 vehicles a day, roughly 1% of them trucks, projected to reach 30,105 by 2040. The structure is 155 ft (47.2 m) long and 94 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Genesee Ave over San Clemente Canyon Crk built?
It was built in 1966, making it 59 years old in 2025. It was reconstructed in 1970.
What condition is Genesee Ave over San Clemente Canyon Crk in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in September 2023.
How much traffic does Genesee Ave over San Clemente Canyon Crk carry?
About 29,800 vehicles per day (2019 count), of which roughly 1% are trucks.
How long is Genesee Ave over San Clemente Canyon Crk?
The structure is 155 ft (47.2 m) long with a longest span of 34 ft (10.4 m) and a deck 94 ft wide.
Who owns Genesee Ave over San Clemente Canyon Crk?
It is owned by the City or Municipal Highway Agency.