S5-E52 Separation over RTE 5 & W52-S5
GoodSan Diego County, California · 11-SD-005-R25.95-SD · Structure no. 57 0463F
- Built
- 1966
- 59 years old
- Condition
- Good
- inspected February 2023
- Type
- Box Beam or Girders - Multiple
- Concrete Continuous
- Length
- 357 ft
- 5 main spans
- Daily traffic
- 12,600
- 2020 count
- Owner
- State
- State Highway Agency
About this bridge
S5-E52 Separation over RTE 5 & W52-S5 is a concrete continuous box beam or girders - multiple carrying S5-E52 Separation over RTE 5 & W52-S5 in San Diego County, California. It was built in 1966, so it is 59 years old, older than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 12,600 vehicles a day, roughly 2% of them trucks, projected to reach 21,422 by 2040. The structure is 357 ft (108.8 m) long and 38 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was S5-E52 Separation over RTE 5 & W52-S5 built?
It was built in 1966, making it 59 years old in 2025.
What condition is S5-E52 Separation over RTE 5 & W52-S5 in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2023.
How much traffic does S5-E52 Separation over RTE 5 & W52-S5 carry?
About 12,600 vehicles per day (2020 count), of which roughly 2% are trucks.
How long is S5-E52 Separation over RTE 5 & W52-S5?
The structure is 357 ft (108.8 m) long with a longest span of 88 ft (26.8 m) and a deck 38 ft wide.
Who owns S5-E52 Separation over RTE 5 & W52-S5?
It is owned by the State Highway Agency.