W94-N5 & F ST-N5 over N5-PERSHING DR & N5-B ST
GoodSan Diego County, California · 11-SD-094-1.46-SD · Structure no. 57 0430F
- Built
- 1962
- 63 years old
- Condition
- Good
- inspected October 2022
- Type
- Box Beam or Girders - Multiple
- Concrete Continuous
- Length
- 140 ft
- 2 main spans
- Daily traffic
- 32,000
- 2016 count
- Owner
- State
- State Highway Agency
About this bridge
W94-N5 & F ST-N5 over N5-PERSHING DR & N5-B ST is a concrete continuous box beam or girders - multiple carrying W94-N5 & F ST-N5 over N5-PERSHING DR & N5-B ST in San Diego County, California. It was built in 1962, so it is 63 years old, older than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 32,000 vehicles a day, roughly 2% of them trucks, projected to reach 43,857 by 2040. The structure is 140 ft (42.7 m) long and 44 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was W94-N5 & F ST-N5 over N5-PERSHING DR & N5-B ST built?
It was built in 1962, making it 63 years old in 2025.
What condition is W94-N5 & F ST-N5 over N5-PERSHING DR & N5-B ST in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in October 2022.
How much traffic does W94-N5 & F ST-N5 over N5-PERSHING DR & N5-B ST carry?
About 32,000 vehicles per day (2016 count), of which roughly 2% are trucks.
How long is W94-N5 & F ST-N5 over N5-PERSHING DR & N5-B ST?
The structure is 140 ft (42.7 m) long with a longest span of 72 ft (21.9 m) and a deck 44 ft wide.
Who owns W94-N5 & F ST-N5 over N5-PERSHING DR & N5-B ST?
It is owned by the State Highway Agency.