E8-MISSION Center over E8-N163 & N163-E8 Ramps
GoodSan Diego County, California · 11-SD-008-2.56-SD · Structure no. 57 0358S
- Built
- 1978
- 47 years old
- Condition
- Good
- inspected February 2024
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete Continuous
- Length
- 745 ft
- 1 main span
- Daily traffic
- 5,800
- 2014 count
- Owner
- State
- State Highway Agency
About this bridge
E8-MISSION Center over E8-N163 & N163-E8 Ramps is a prestressed concrete continuous box beam or girders - multiple carrying E8-MISSION Center over E8-N163 & N163-E8 Ramps in San Diego County, California. It was built in 1978, so it is 47 years old, younger than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 5,800 vehicles a day, roughly 2% of them trucks, projected to reach 10,977 by 2046. The structure is 745 ft (227.1 m) long and 28 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was E8-MISSION Center over E8-N163 & N163-E8 Ramps built?
It was built in 1978, making it 47 years old in 2025.
What condition is E8-MISSION Center over E8-N163 & N163-E8 Ramps in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2024.
How much traffic does E8-MISSION Center over E8-N163 & N163-E8 Ramps carry?
About 5,800 vehicles per day (2014 count), of which roughly 2% are trucks.
How long is E8-MISSION Center over E8-N163 & N163-E8 Ramps?
The structure is 745 ft (227.1 m) long with a longest span of 214 ft (65.2 m) and a deck 28 ft wide.
Who owns E8-MISSION Center over E8-N163 & N163-E8 Ramps?
It is owned by the State Highway Agency.