US Bridges

Interstate 15 over Ontario Mills Parkway

Fair

San Bernardino County, California · 08-SBD-015-2.56-ONT · Structure no. 54 0911

Built
1975
50 years old, rebuilt 2011
Condition
Fair
inspected February 2024
Type
Box Beam or Girders - Multiple
Prestressed Concrete
Length
123 ft
1 main span
Daily traffic
211,000
2022 count
Owner
State
State Highway Agency

About this bridge

Interstate 15 over Ontario Mills Parkway is a prestressed concrete box beam or girders - multiple carrying Interstate 15 over Ontario Mills Parkway in San Bernardino County, California. It was built in 1975 and reconstructed in 2011, so it is 50 years old, younger than the California average of 54.8 years.

The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

It carries about 211,000 vehicles a day, roughly 10% of them trucks, projected to reach 220,015 by 2042. The structure is 123 ft (37.5 m) long and 230 ft wide. If it were closed, the detour would be 1.2 mi (2 km).

CarriesInterstate 15
CrossesOntario Mills Parkway
Location08-SBD-015-2.56-ONT
RouteInterstate 15
Coordinates34.06983, -117.54489
Functional classUrban Principal Arterial - Interstate

Condition and inspection

Fair

The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Substructure7 GoodSome minor problems.
Last inspectionFebruary 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation5: Somewhat better than minimum adequacy to tolerate being left in place as is
Deck geometry9: Superior to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating56.8 US tons
Inventory rating43.5 US tons

Structure

MaterialPrestressed Concrete
DeckConcrete, cast-in-place
Main spans1
Design loadHS 20 + Mod
Structure length123 ft (37.5 m)
Longest span123 ft (37.5 m)
Deck width230 ft (70 m)
Roadway width225 ft (68.5 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic211,000 (2022)
Projected traffic220,015 by 2042
Trucks10%
Lanes on structure11
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed1.2 mi (2 km)
TollOn a free road
National Highway SystemYes
Strategic Highway NetworkInterstate STRAHNET route

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNot applicable (no waterway)

Frequently asked questions

When was Interstate 15 over Ontario Mills Parkway built?

It was built in 1975, making it 50 years old in 2025. It was reconstructed in 2011.

What condition is Interstate 15 over Ontario Mills Parkway in?

The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in February 2024.

How much traffic does Interstate 15 over Ontario Mills Parkway carry?

About 211,000 vehicles per day (2022 count), of which roughly 10% are trucks.

How long is Interstate 15 over Ontario Mills Parkway?

The structure is 123 ft (37.5 m) long with a longest span of 123 ft (37.5 m) and a deck 230 ft wide.

Who owns Interstate 15 over Ontario Mills Parkway?

It is owned by the State Highway Agency.