S5-J ST Off-Ramp over Parking Garage Access
GoodSacramento County, California · 03-SAC-005-23.68-SAC · Structure no. 24 0352K
- Built
- 1982
- 43 years old
- Condition
- Good
- inspected February 2025
- Type
- Slab
- Concrete
- Length
- 25 ft
- 1 main span
- Daily traffic
- 9,000
- 2015 count
- Owner
- State
- State Highway Agency
About this bridge
S5-J ST Off-Ramp over Parking Garage Access is a concrete slab carrying S5-J ST Off-Ramp over Parking Garage Access in Sacramento County, California. It was built in 1982, so it is 43 years old, younger than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 9,000 vehicles a day, roughly 2% of them trucks, projected to reach 10,618 by 2047. The structure is 25 ft (7.6 m) long and 58 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was S5-J ST Off-Ramp over Parking Garage Access built?
It was built in 1982, making it 43 years old in 2025.
What condition is S5-J ST Off-Ramp over Parking Garage Access in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2025.
How much traffic does S5-J ST Off-Ramp over Parking Garage Access carry?
About 9,000 vehicles per day (2015 count), of which roughly 2% are trucks.
How long is S5-J ST Off-Ramp over Parking Garage Access?
The structure is 25 ft (7.6 m) long with a longest span of 25 ft (7.6 m) and a deck 58 ft wide.
Who owns S5-J ST Off-Ramp over Parking Garage Access?
It is owned by the State Highway Agency.