Watt EB 50 On-Ramp over Bicycle &pedestrian Path
GoodSacramento County, California · 03-SAC-050-R5.40-SAC · Structure no. 24 0034T
- Built
- 2015
- 10 years old
- Condition
- Good
- inspected November 2023
- Type
- Slab
- Concrete
- Length
- 36 ft
- 1 main span
- Daily traffic
- 20,000
- 2009 count
- Owner
- State
- State Highway Agency
About this bridge
Watt EB 50 On-Ramp over Bicycle &pedestrian Path is a concrete slab carrying Watt EB 50 On-Ramp over Bicycle &pedestrian Path in Sacramento County, California. It was built in 2015, so it is 10 years old, younger than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 20,000 vehicles a day, roughly 6% of them trucks, projected to reach 31,326 by 2045. The structure is 36 ft (11.1 m) long and 39 ft wide. If it were closed, the detour would be 6.2 mi (10 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Watt EB 50 On-Ramp over Bicycle &pedestrian Path built?
It was built in 2015, making it 10 years old in 2025.
What condition is Watt EB 50 On-Ramp over Bicycle &pedestrian Path in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in November 2023.
How much traffic does Watt EB 50 On-Ramp over Bicycle &pedestrian Path carry?
About 20,000 vehicles per day (2009 count), of which roughly 6% are trucks.
How long is Watt EB 50 On-Ramp over Bicycle &pedestrian Path?
The structure is 36 ft (11.1 m) long with a longest span of 35 ft (10.7 m) and a deck 39 ft wide.
Who owns Watt EB 50 On-Ramp over Bicycle &pedestrian Path?
It is owned by the State Highway Agency.