Main Street over Temescal Creek Channel
GoodRiverside County, California · 0.2 Mi. N/O River Road · Structure no. 56C0441
- Built
- 1972
- 53 years old
- Condition
- Good
- inspected December 2022
- Type
- Tee Beam
- Prestressed Concrete Continuous
- Length
- 160 ft
- 3 main spans
- Daily traffic
- 34,000
- 2020 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
Main Street over Temescal Creek Channel is a prestressed concrete continuous tee beam carrying Main Street over Temescal Creek Channel in Riverside County, California. It was built in 1972, so it is 53 years old, younger than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 34,000 vehicles a day, roughly 2% of them trucks, projected to reach 71,719 by 2041. The structure is 160 ft (48.8 m) long and 93 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Main Street over Temescal Creek Channel built?
It was built in 1972, making it 53 years old in 2025.
What condition is Main Street over Temescal Creek Channel in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in December 2022.
How much traffic does Main Street over Temescal Creek Channel carry?
About 34,000 vehicles per day (2020 count), of which roughly 2% are trucks.
How long is Main Street over Temescal Creek Channel?
The structure is 160 ft (48.8 m) long with a longest span of 53 ft (16.2 m) and a deck 93 ft wide.
Who owns Main Street over Temescal Creek Channel?
It is owned by the City or Municipal Highway Agency.