NB 5 LA Paz Offrmp over Bnsf/Mtrlink/El Toro Crk
GoodOrange County, California · 12-ORA-005-16.37-MSNV · Structure no. 55 1108S
- Built
- 2024
- 1 years old
- Condition
- Good
- inspected July 2024
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete Continuous
- Length
- 382 ft
- 3 main spans
- Daily traffic
- 5,290
- 2022 count
- Owner
- State
- State Highway Agency
About this bridge
NB 5 LA Paz Offrmp over Bnsf/Mtrlink/El Toro Crk is a prestressed concrete continuous box beam or girders - multiple carrying NB 5 LA Paz Offrmp over Bnsf/Mtrlink/El Toro Crk in Orange County, California. It was built in 2024, so it is 1 years old, younger than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 5,290 vehicles a day, roughly 7% of them trucks, projected to reach 8,500 by 2044. The structure is 382 ft (116.4 m) long and 33 ft wide. If it were closed, the detour would be 2.5 mi (4 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was NB 5 LA Paz Offrmp over Bnsf/Mtrlink/El Toro Crk built?
It was built in 2024, making it 1 years old in 2025.
What condition is NB 5 LA Paz Offrmp over Bnsf/Mtrlink/El Toro Crk in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in July 2024.
How much traffic does NB 5 LA Paz Offrmp over Bnsf/Mtrlink/El Toro Crk carry?
About 5,290 vehicles per day (2022 count), of which roughly 7% are trucks.
How long is NB 5 LA Paz Offrmp over Bnsf/Mtrlink/El Toro Crk?
The structure is 382 ft (116.4 m) long with a longest span of 143 ft (43.5 m) and a deck 33 ft wide.
Who owns NB 5 LA Paz Offrmp over Bnsf/Mtrlink/El Toro Crk?
It is owned by the State Highway Agency.