Molera RD over SR 1 S1-MOLERA Offramp
GoodMonterey County, California · 05-MON-001-R90.39 · Structure no. 44 0217
- Built
- 1976
- 49 years old
- Condition
- Good
- inspected August 2023
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete Continuous
- Length
- 362 ft
- 2 main spans
- Daily traffic
- 2,400
- 2005 count
- Owner
- State
- State Highway Agency
About this bridge
Molera RD over SR 1 S1-MOLERA Offramp is a prestressed concrete continuous box beam or girders - multiple carrying Molera RD over SR 1 S1-MOLERA Offramp in Monterey County, California. It was built in 1976, so it is 49 years old, younger than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 2,400 vehicles a day, roughly 2% of them trucks, projected to reach 5,292 by 2043. The structure is 362 ft (110.3 m) long and 47 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Molera RD over SR 1 S1-MOLERA Offramp built?
It was built in 1976, making it 49 years old in 2025.
What condition is Molera RD over SR 1 S1-MOLERA Offramp in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2023.
How much traffic does Molera RD over SR 1 S1-MOLERA Offramp carry?
About 2,400 vehicles per day (2005 count), of which roughly 2% are trucks.
How long is Molera RD over SR 1 S1-MOLERA Offramp?
The structure is 362 ft (110.3 m) long with a longest span of 194 ft (59.1 m) and a deck 47 ft wide.
Who owns Molera RD over SR 1 S1-MOLERA Offramp?
It is owned by the State Highway Agency.