Sullivan Road over Ccid Main Canal
FairMerced County, California · 50 Ft E of SR140 & SR33 · Structure no. 39C0361
- Built
- 1996
- 29 years old
- Condition
- Fair
- inspected February 2023
- Type
- Slab
- Concrete Continuous
- Length
- 75 ft
- 3 main spans
- Daily traffic
- 1,101
- 2014 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
Sullivan Road over Ccid Main Canal is a concrete continuous slab carrying Sullivan Road over Ccid Main Canal in Merced County, California. It was built in 1996, so it is 29 years old, younger than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 1,101 vehicles a day, roughly 6% of them trucks, projected to reach 1,580 by 2045. The structure is 75 ft (22.9 m) long and 52 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Sullivan Road over Ccid Main Canal built?
It was built in 1996, making it 29 years old in 2025.
What condition is Sullivan Road over Ccid Main Canal in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in February 2023.
How much traffic does Sullivan Road over Ccid Main Canal carry?
About 1,101 vehicles per day (2014 count), of which roughly 6% are trucks.
How long is Sullivan Road over Ccid Main Canal?
The structure is 75 ft (22.9 m) long with a longest span of 29 ft (8.8 m) and a deck 52 ft wide.
Who owns Sullivan Road over Ccid Main Canal?
It is owned by the City or Municipal Highway Agency.