135th ST over Dominguez Hollypark Chan
FairLos Angeles County, California · 200FT E/O Crenshaw Blvd · Structure no. 53C1458
- Built
- 1961
- 64 years old
- Condition
- Fair
- inspected July 2023
- Type
- Slab
- Concrete Continuous
- Length
- 110 ft
- 4 main spans
- Daily traffic
- 11,615
- 2013 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
135th ST over Dominguez Hollypark Chan is a concrete continuous slab carrying 135th ST over Dominguez Hollypark Chan in Los Angeles County, California. It was built in 1961, so it is 64 years old, older than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 11,615 vehicles a day, roughly 2% of them trucks, projected to reach 13,357 by 2043. The structure is 110 ft (33.5 m) long and 70 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 9 Excellent | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was 135th ST over Dominguez Hollypark Chan built?
It was built in 1961, making it 64 years old in 2025.
What condition is 135th ST over Dominguez Hollypark Chan in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in July 2023.
How much traffic does 135th ST over Dominguez Hollypark Chan carry?
About 11,615 vehicles per day (2013 count), of which roughly 2% are trucks.
How long is 135th ST over Dominguez Hollypark Chan?
The structure is 110 ft (33.5 m) long with a longest span of 49 ft (14.9 m) and a deck 70 ft wide.
Who owns 135th ST over Dominguez Hollypark Chan?
It is owned by the City or Municipal Highway Agency.