State Route 269 over Arroyo Pasajero Creek
GoodFresno County, California · 06-FRE-269-11.23 · Structure no. 42 0452
- Built
- 2019
- 6 years old
- Condition
- Good
- inspected January 2025
- Type
- Slab
- Concrete Continuous
- Length
- 500 ft
- 13 main spans
- Daily traffic
- 4,500
- 2017 count
- Owner
- State
- State Highway Agency
About this bridge
State Route 269 over Arroyo Pasajero Creek is a concrete continuous slab carrying State Route 269 over Arroyo Pasajero Creek in Fresno County, California. It was built in 2019, so it is 6 years old, younger than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 4,500 vehicles a day, roughly 15% of them trucks, projected to reach 7,141 by 2043. The structure is 500 ft (152.4 m) long and 43 ft wide. If it were closed, the detour would be 4.3 mi (7 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was State Route 269 over Arroyo Pasajero Creek built?
It was built in 2019, making it 6 years old in 2025.
What condition is State Route 269 over Arroyo Pasajero Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in January 2025.
How much traffic does State Route 269 over Arroyo Pasajero Creek carry?
About 4,500 vehicles per day (2017 count), of which roughly 15% are trucks.
How long is State Route 269 over Arroyo Pasajero Creek?
The structure is 500 ft (152.4 m) long with a longest span of 40 ft (12.2 m) and a deck 43 ft wide.
Who owns State Route 269 over Arroyo Pasajero Creek?
It is owned by the State Highway Agency.