US Bridges

E Rio Bonito Road over Sutter-Butte Canal

Poor

Butte County, California · 0.8 MI East of SR 99 · Structure no. 12C0165

Built
1974
51 years old
Condition
Poor
inspected February 2025
Type
Stringer/Multi-beam or Girder
Steel Continuous
Length
37 ft
2 main spans
Daily traffic
270
2017 count
Owner
County
County Highway Agency

About this bridge

E Rio Bonito Road over Sutter-Butte Canal is a steel continuous stringer/multi-beam or girder carrying E Rio Bonito Road over Sutter-Butte Canal in Butte County, California. It was built in 1974, so it is 51 years old, younger than the California average of 54.8 years.

The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 4 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.

It carries about 270 vehicles a day, roughly 2% of them trucks, projected to reach 436 by 2045. The structure is 37 ft (11.3 m) long and 18 ft wide. If it were closed, the detour would be 5 mi (8 km).

CarriesE Rio Bonito Road
CrossesSutter-Butte Canal
Location0.8 MI East of SR 99
RouteCounty Highway 0
Coordinates39.42788, -121.67819
Functional classRural Local

Condition and inspection

Poor

The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure4 PoorAdvanced section loss, deterioration, spalling or scour.
Substructure5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Channel and channel protection8 Very GoodNo problems noted.
Last inspectionFebruary 2025
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourUnknown foundation; not evaluated for scour
Structural evaluation4: Meets minimum tolerable limits to be left in place as is
Deck geometry2: Basically intolerable, requiring high priority of replacement
Waterway adequacy9: Superior to present desirable criteria
Approach roadway alignment6: Equal to present minimum criteria
Operating rating17.5 US tons
Inventory rating13.6 US tons

Structure

MaterialSteel Continuous
DeckWood or timber
Main spans2
Design loadUnknown
Structure length37 ft (11.3 m)
Longest span18 ft (5.4 m)
Deck width18 ft (5.5 m)
Roadway width17 ft (5.3 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic270 (2017)
Projected traffic436 by 2045
Trucks2%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed5 mi (8 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCounty Highway Agency
Maintained byCounty Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedReplacement because of substandard load-carrying capacity or roadway geometry
Estimated improvement cost$235,000 (2017 estimate)
NavigationNo navigation control on waterway

Frequently asked questions

When was E Rio Bonito Road over Sutter-Butte Canal built?

It was built in 1974, making it 51 years old in 2025.

What condition is E Rio Bonito Road over Sutter-Butte Canal in?

The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in February 2025.

How much traffic does E Rio Bonito Road over Sutter-Butte Canal carry?

About 270 vehicles per day (2017 count), of which roughly 2% are trucks.

How long is E Rio Bonito Road over Sutter-Butte Canal?

The structure is 37 ft (11.3 m) long with a longest span of 18 ft (5.4 m) and a deck 18 ft wide.

Who owns E Rio Bonito Road over Sutter-Butte Canal?

It is owned by the County Highway Agency.