Chandler Hghts RD over Sonoqui Wash
GoodMaricopa County, Arizona · 0.4 Mi. E/ of Sossaman R · Structure no. 10777
- Built
- 2008
- 17 years old
- Condition
- Good
- inspected November 2022
- Type
- Box Beam or Girders - Single or Spread
- Prestressed Concrete Continuous
- Length
- 186 ft
- 3 main spans
- Daily traffic
- 7,300
- 2021 count
- Owner
- Town / Township
- Town or Township Highway Agency
About this bridge
Chandler Hghts RD over Sonoqui Wash is a prestressed concrete continuous box beam or girders - single or spread carrying Chandler Hghts RD over Sonoqui Wash in Maricopa County, Arizona. It was built in 2008, so it is 17 years old, younger than the Arizona average of 47.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 7,300 vehicles a day, roughly 10% of them trucks, projected to reach 7,310 by 2041. The structure is 186 ft (56.8 m) long and 89 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Chandler Hghts RD over Sonoqui Wash built?
It was built in 2008, making it 17 years old in 2025.
What condition is Chandler Hghts RD over Sonoqui Wash in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in November 2022.
How much traffic does Chandler Hghts RD over Sonoqui Wash carry?
About 7,300 vehicles per day (2021 count), of which roughly 10% are trucks.
How long is Chandler Hghts RD over Sonoqui Wash?
The structure is 186 ft (56.8 m) long with a longest span of 68 ft (20.7 m) and a deck 89 ft wide.
Who owns Chandler Hghts RD over Sonoqui Wash?
It is owned by the Town or Township Highway Agency.