US 63-13 Lm 3.24 over Plum Bayou-Jefferson CO
GoodJefferson County, Arkansas · 3.0 MI S US79B-ALTHIEMER · Structure no. 000000000006566
- Built
- 1998
- 27 years old
- Condition
- Good
- inspected August 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 414 ft
- 4 main spans
- Daily traffic
- 3,700
- 2018 count
- Owner
- State
- State Highway Agency
About this bridge
US 63-13 Lm 3.24 over Plum Bayou-Jefferson CO is a steel continuous stringer/multi-beam or girder carrying US 63-13 Lm 3.24 over Plum Bayou-Jefferson CO in Jefferson County, Arkansas. It was built in 1998, so it is 27 years old, younger than the Arkansas average of 45.1 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 3,700 vehicles a day, roughly 18% of them trucks, projected to reach 4,814 by 2028. The structure is 414 ft (126.3 m) long and 43 ft wide. If it were closed, the detour would be 24.9 mi (40 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was US 63-13 Lm 3.24 over Plum Bayou-Jefferson CO built?
It was built in 1998, making it 27 years old in 2025.
What condition is US 63-13 Lm 3.24 over Plum Bayou-Jefferson CO in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2024.
How much traffic does US 63-13 Lm 3.24 over Plum Bayou-Jefferson CO carry?
About 3,700 vehicles per day (2018 count), of which roughly 18% are trucks.
How long is US 63-13 Lm 3.24 over Plum Bayou-Jefferson CO?
The structure is 414 ft (126.3 m) long with a longest span of 119 ft (36.3 m) and a deck 43 ft wide.
Who owns US 63-13 Lm 3.24 over Plum Bayou-Jefferson CO?
It is owned by the State Highway Agency.