CR 500 - a over Drainage Ditch
GoodPosted for loadClay County, Arkansas · 4 MI So. of Rector · Structure no. 000000000022284
- Built
- 2001
- 24 years old
- Condition
- Good
- inspected July 2024
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 101 ft
- 2 main spans
- Daily traffic
- 11
- 2018 count
- Owner
- County
- County Highway Agency
About this bridge
CR 500 - a over Drainage Ditch is a steel stringer/multi-beam or girder carrying CR 500 - a over Drainage Ditch in Clay County, Arkansas. It was built in 2001, so it is 24 years old, younger than the Arkansas average of 45.1 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. Its operating status is: posted for load restriction.
It carries about 11 vehicles a day, roughly 1% of them trucks, projected to reach 22 by 2007. The structure is 101 ft (30.7 m) long and 20 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was CR 500 - a over Drainage Ditch built?
It was built in 2001, making it 24 years old in 2025.
What condition is CR 500 - a over Drainage Ditch in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in July 2024.
How much traffic does CR 500 - a over Drainage Ditch carry?
About 11 vehicles per day (2018 count), of which roughly 1% are trucks.
How long is CR 500 - a over Drainage Ditch?
The structure is 101 ft (30.7 m) long with a longest span of 59 ft (18.1 m) and a deck 20 ft wide.
Who owns CR 500 - a over Drainage Ditch?
It is owned by the County Highway Agency.