IRR BIA RTE 28 over Unnamed Stream
GoodPrince of Wales-Hyder Census Area, Alaska · 11.8KM Down Fs 6328 · Structure no. 0000E09229T0330
- Built
- 1990
- 35 years old
- Condition
- Good
- inspected September 2024
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 80 ft
- 1 main span
- Daily traffic
- 5
- 2019 count
- Owner
- Tribal
- Indian Tribal Government
About this bridge
IRR BIA RTE 28 over Unnamed Stream is a steel stringer/multi-beam or girder carrying IRR BIA RTE 28 over Unnamed Stream in Prince of Wales-Hyder Census Area, Alaska. It was built in 1990, so it is 35 years old, younger than the Alaska average of 35.9 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 5 vehicles a day, projected to reach 10 by 2041. The structure is 80 ft (24.5 m) long and 16 ft wide. If it were closed, the detour would be 123.7 mi (199 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was IRR BIA RTE 28 over Unnamed Stream built?
It was built in 1990, making it 35 years old in 2025.
What condition is IRR BIA RTE 28 over Unnamed Stream in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in September 2024.
How much traffic does IRR BIA RTE 28 over Unnamed Stream carry?
About 5 vehicles per day (2019 count).
How long is IRR BIA RTE 28 over Unnamed Stream?
The structure is 80 ft (24.5 m) long with a longest span of 78 ft (23.9 m) and a deck 16 ft wide.
Who owns IRR BIA RTE 28 over Unnamed Stream?
It is owned by the Indian Tribal Government.