IRR BIA RTE 1 over Tent Creek

Fair

Prince of Wales-Hyder Census Area, Alaska · 10.5 KM SE of Metlakatla · Structure no. 00000000000P651

Built
1993
32 years old
Condition
Fair
inspected September 2021
Type
Stringer/Multi-beam or Girder
Steel
Length
67 ft
1 main span
Daily traffic
35
2021 count
Owner
Federal
Bureau of Indian Affairs

About this bridge

IRR BIA RTE 1 over Tent Creek is a steel stringer/multi-beam or girder carrying IRR BIA RTE 1 over Tent Creek in Prince of Wales-Hyder Census Area, Alaska. It was built in 1993, so it is 32 years old, younger than the Alaska average of 35.9 years.

The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

It carries about 35 vehicles a day, roughly 5% of them trucks, projected to reach 41 by 2040. The structure is 67 ft (20.5 m) long and 18 ft wide. If it were closed, the detour would be 123.7 mi (199 km).

CarriesIRR BIA RTE 1
CrossesTent Creek
Location10.5 KM SE of Metlakatla
RouteFederal Lands Road 1
StateAlaska
Coordinates55.06681, -131.52172
Functional classRural Local

Condition and inspection

Fair

The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

ComponentRatingMeaning
Deck5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Superstructure5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Substructure6 SatisfactoryStructural elements show some minor deterioration.
Channel and channel protection8 Very GoodNo problems noted.
Last inspectionSeptember 2021
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation5: Somewhat better than minimum adequacy to tolerate being left in place as is
Waterway adequacy9: Superior to present desirable criteria
Approach roadway alignment6: Equal to present minimum criteria
Operating rating39.4 US tons
Inventory rating23.6 US tons

Structure

MaterialSteel
DeckConcrete, cast-in-place
Main spans1
Design loadHS 20
Structure length67 ft (20.5 m)
Longest span62 ft (18.8 m)
Deck width18 ft (5.4 m)
Roadway width17 ft (5.2 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic35 (2021)
Projected traffic41 by 2040
Trucks5%
Lanes on structure2
Traffic directionOne-lane bridge for two-way traffic
CarriesHighway
CrossesWaterway
Detour if closed123.7 mi (199 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerBureau of Indian Affairs
Maintained byBureau of Indian Affairs
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNot applicable (no waterway)

Frequently asked questions

When was IRR BIA RTE 1 over Tent Creek built?

It was built in 1993, making it 32 years old in 2025.

What condition is IRR BIA RTE 1 over Tent Creek in?

The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in September 2021.

How much traffic does IRR BIA RTE 1 over Tent Creek carry?

About 35 vehicles per day (2021 count), of which roughly 5% are trucks.

How long is IRR BIA RTE 1 over Tent Creek?

The structure is 67 ft (20.5 m) long with a longest span of 62 ft (18.8 m) and a deck 18 ft wide.

Who owns IRR BIA RTE 1 over Tent Creek?

It is owned by the Bureau of Indian Affairs.