Matanuska-Susitna Borough, Alaska · Mile Point 2.6 · Structure no. 2034

Built
2003
22 years old
Condition
Good
inspected June 2024
Type
Tee Beam
Prestressed Concrete
Length
85 ft
1 main span
Daily traffic
13,200
2020 count
Owner
State
State Highway Agency

About this bridge

Parks Highway over Hyer RD Uc Northbound is a prestressed concrete tee beam carrying Parks Highway over Hyer RD Uc Northbound in Matanuska-Susitna Borough, Alaska. It was built in 2003, so it is 22 years old, younger than the Alaska average of 35.9 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 13,200 vehicles a day, roughly 5% of them trucks, projected to reach 15,300 by 2039. The structure is 85 ft (26 m) long and 40 ft wide. If it were closed, the detour would be 1.2 mi (2 km).

CarriesParks Highway
CrossesHyer RD Uc Northbound
LocationMile Point 2.6
RouteInterstate 0A41
StateAlaska
Coordinates61.5679, -149.31321
Functional classUrban Principal Arterial - Interstate

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck8 Very GoodNo problems noted.
Superstructure8 Very GoodNo problems noted.
Substructure7 GoodSome minor problems.
Last inspectionJune 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation7: Better than present minimum criteria
Deck geometry5: Somewhat better than minimum adequacy to tolerate being left in place as is
Approach roadway alignment7: Better than present minimum criteria
Operating rating110.1 US tons
Inventory rating53.6 US tons

Structure

Structure typeTee Beam
MaterialPrestressed Concrete
DeckOther
Main spans1
Design loadHS 25 or greater
Structure length85 ft (26 m)
Longest span80 ft (24.5 m)
Deck width40 ft (12.3 m)
Roadway width37 ft (11.4 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic13,200 (2020)
Projected traffic15,300 by 2039
Trucks5%
Lanes on structure2
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed1.2 mi (2 km)
TollOn a free road
National Highway SystemYes

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNot applicable (no waterway)

Frequently asked questions

When was Parks Highway over Hyer RD Uc Northbound built?

It was built in 2003, making it 22 years old in 2025.

What condition is Parks Highway over Hyer RD Uc Northbound in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in June 2024.

How much traffic does Parks Highway over Hyer RD Uc Northbound carry?

About 13,200 vehicles per day (2020 count), of which roughly 5% are trucks.

How long is Parks Highway over Hyer RD Uc Northbound?

The structure is 85 ft (26 m) long with a longest span of 80 ft (24.5 m) and a deck 40 ft wide.

Who owns Parks Highway over Hyer RD Uc Northbound?

It is owned by the State Highway Agency.