Irr:summer Bay RD over Summer Bay Creek
GoodPosted for loadAleutians West Census Area, Alaska · Mile Point 0.1 · Structure no. 1686
- Built
- 2014
- 11 years old
- Condition
- Good
- inspected September 2024
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 70 ft
- 1 main span
- Daily traffic
- 400
- 2020 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
Irr:summer Bay RD over Summer Bay Creek is a steel stringer/multi-beam or girder carrying Irr:summer Bay RD over Summer Bay Creek in Aleutians West Census Area, Alaska. It was built in 2014, so it is 11 years old, younger than the Alaska average of 35.9 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. Its operating status is: posted for load restriction.
It carries about 400 vehicles a day, roughly 14% of them trucks, projected to reach 1,310 by 2039. The structure is 70 ft (21.3 m) long and 26 ft wide. If it were closed, the detour would be 123.7 mi (199 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 9 Excellent | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 9 Excellent | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Irr:summer Bay RD over Summer Bay Creek built?
It was built in 2014, making it 11 years old in 2025.
What condition is Irr:summer Bay RD over Summer Bay Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in September 2024.
How much traffic does Irr:summer Bay RD over Summer Bay Creek carry?
About 400 vehicles per day (2020 count), of which roughly 14% are trucks.
How long is Irr:summer Bay RD over Summer Bay Creek?
The structure is 70 ft (21.3 m) long with a longest span of 64 ft (19.5 m) and a deck 26 ft wide.
Who owns Irr:summer Bay RD over Summer Bay Creek?
It is owned by the City or Municipal Highway Agency.